David Pennington

Week Of Contribution
February 10th Built website using Github Pages, met with group at Awesome In
February 17th Updated site. Started on iOS App for Bus Alert
February 24th Worked on iOS App, added map functionality.
March 3rd Worked on iOS App, added more map functionality.
March 10st Worked on iOS App, added more map functionality.
March 17st Worked on iOS App, added more map functionality.
March 24st Worked on iOS App, added more map functionality.
March 31st Worked on iOS App, added more map functionality.
April 7 Testing of iOS App
April 14 Made Presentation
April 21 Presentation Practice. documentation. Writing Final Report

Alex Henry

Week Of Contribution
February 10th Organized meeting with team members and mentor. Worked on the information on the site.
February 17th Further updated the site and added information to bring it to a more "final" state. Began initial implementation of Android side of the app.
February 24th Began the implementation of the Android application.
March 3rd Continue work on Android app and start Design Document. Worked on midterm presentation.
March 10th Worked on menu design of android app. Looked at the Lextrain API querying.
March 17th Implemented the functionality of communicating with the Lextran API.
March 24th Implemented drawing the stops on the map. Also implemented the estimated bus arrivals for each stop.
March 31st Tweak the map display. Working on the notification service for the app.
April 7th Continue work on notification. Tweak the display of each stop on the map view.
April 14th Polish notification. Work on signing the application for public release.

Robert Burrus

Week Of Contribution
February 10th Brainstormed for project ideas with teammates / mentor. Made small changes to web site. Familiarized myself with github and jekyll.
February 17th Made small changes to website and brainstormed about potential bus alert functionality and implementation.
February 24th Started implementation of Android Bus Alert App. Started project presentation powerpoint.
March 3 Worked on Android app, created design page.
March 10 Worked on Android app, started creating parser for KML files.
March 17 Spring Break.
March 24 Worked on Android app: worked on issues with Google maps and android emulator, worked on overlaying KML data on Google Maps.
March 31 Began work on notification.
April 7 Continued work on notification / AlarmManager / NotifyService
April 14 Finished notification. Began testing of notification.
April 21 Presentation Practice. Clean up code / add documentation.